Document control record
Document prepared by:
Company name
Registration number
Address line 1
Address line 2
Address line 3
T |
Company
telephone |
A person using Aurecon documents or data accepts the risk of:
a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version.
b) Using the documents or data for any purpose not agreed to in writing by Aurecon.
Report title |
Quarterly Environmental Monitoring and Audit (EM&A) Report |
|||||
Document code |
EM&A-01 |
Project number |
P525672 |
|||
File path |
|
|||||
Client |
Wing Tat Civil Engineering Co. Limited |
|||||
Client contact |
|
Client reference |
|
|||
Author |
Reviewer |
Verifier
|
||||
0 |
2024-07-17 |
First Issue |
Jason Man |
F. C. Tsang |
|
Kevin Li |
1 |
2024-07-31 |
Second Issue |
Jason Man |
F. C. Tsang |
|
Kevin Li |
2 |
2024-08-19 |
Second Issue |
Jason Man |
F. C. Tsang |
|
Kevin Li |
|
|
|
|
|
|
|
Author signature |
|
Certified by |
|
Name |
Jason Man |
Name |
F. C. Tsang |
Title |
Environmental Team Consultant |
Title |
Environmental Team Leader |
Contents
1.2 Construction Works Programme
1.4 Construction Works Programme and Construction Works Area
1.5 Works undertaken during the Period
2.3 Monitoring Parameter and Frequency
2.4 Action and Limit Level for Water Quality Monitoring
2.7 Quarterly Assessment of Construction Impacts on Suspended Solids at the Project Site
3.2 Noise Monitoring Parameter, Frequency and Duration
9 Environmental Site Inspection and Audit
9.1 Implementation Status of Environmental Mitigation Measures
10 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
10.2 Summary of Environmental Non-Compliance
10.3 Summary of Environmental Complaint
10.4 Summary of Environmental Summon and Successful Prosecution
11 Conclusions and Recommendations
11.2 Comments/ Recommendations
Appendices
Appendix 1.1 Construction Programme
Appendix 1.2 Project Organization Chart
Appendix 2.1 Event and Action Plans for Water Quality
Appendix 2.2 Graphical Presentation of Water Quality Monitoring
Appendix 3.1 Event and Action Plans for Noise
Appendix 3.2 Graphical Presentation of Noise Monitoring
Figures
Figure 1.1 General Site Location Plan
Figure 1.2 Location of Work Areas for the Project
Figure 2.1 Impact Water Quality Monitoring Locations
Figure 3.1 Impact Noise Monitoring Locations
Figure 8.1 Area for Archaeological Survey
Tables
Table A1 Summary of Exceedance Records of Water Quality Monitoring
Table 1.1 Parties Involved in Project Organisation
Table 2.1 Summary of Impact Water Quality Monitoring Stations
Table 2.2 Parameters measured in the Impact Water Quality Monitoring
Table 2.3 Action and Limit Levels for Water Quality
Table 2.4 Action and Limit Levels of Water Quality
Table 2.5 Summary of Exceedance Records of Water Quality Monitoring
Table 3.1 Noise Monitoring Stations during Construction Phase
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
Table 3.3 Action and Limit Levels for Construction Noise Monitoring
Table 8.1 Mitigation Measures for Impacted Graded Historic Buildings
Table 10.1 Summary of Exceedance Records of Water Quality Monitoring
A1. Drainage Services Department (DSD) has appointed Aurecon Hong Kong Limited (Aurecon) to undertake the Environmental Team services for the project and implement the EM&A works.
A2. The construction works commenced on 20 February 2024.
A3. This 1st Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. DC/2022/02 Drainage Improvement Works at Yuen Long – Stage 2 (hereinafter called the “Contract”). The report summaries the findings of the EM&A programme during the reporting period from 20 February to 30 April 2024.
A4. A summary of construction activities undertaken during the reporting period is presented below:
Ha Che
§ Site Clearance Work
§ Lifting Operation;
§ Plant Operation;
§ Excavation; and
§ Sheet Piling.
Lin Fa Tei
§ Site Clearance Work
§ Lifting Operation;
§ Plant Operation; and
§ Excavation.
Tai Wo
§ No construction activities.
Sung Shan New Village
§ No construction activities.
Water Quality
A5. The summary of exceedance records during the reporting period is summarized in Table A1.
Table A1 Summary of Exceedance Records of Water Quality Monitoring
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedance related to the Project |
Total No. of exceedance related to the Project |
||
AL |
LL |
AL |
LL |
|||
Dissolved Oxygen |
2 |
1 |
3 |
0 |
0 |
0 |
Turbidity |
0 |
1 |
1 |
0 |
0 |
0 |
Suspended Solids |
2 |
11 |
13 |
0 |
0 |
0 |
A6. Two (2) action level and One (1) limit level exceedances for DO, One (1) limit level exceedances for Turbidity and Two (2) action level and Eleven (11) limit level exceedances for SS were recorded during the reporting period. After investigation of above the exceedances, it was considered to non-project related.
Noise
A7. No Action Level or Limit Level exceedance was recorded for construction noise monitoring during the reporting period.
A8. No environmental complaint was received in the reporting period.
A9. No notification of summons or successful prosecutions was received in the reporting period.
A10. Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No.: EP-596/2021. Thus, the construction EM&A programme at Tai Wo, including impact water quality monitoring, impact noise monitoring and weekly inspection, are temporarily suspended starting from 1 April 2024.
A11. Construction work at Sung Shan New Village was commenced on 16 April 2024 and the construction phase EM&A programme at Sung Shan New Village started on 16 April 2024.
A12. The noise monitoring at LFT_M7 have been suspended since 27 March 2024 due to the objection from property management office for providing access to designated monitoring location. The noise monitoring at LFT_M7 will be resumed when the access to the monitoring location is granted.
Diagram 1.1 Organisation Chart
Table 1.1 Parties Involved in Project Organisation
Parties |
Organization / Company |
Project Proponent |
Drainage Services Department |
Supervisor / Engineer’s Representative (ER) |
Atkins China Ltd |
Contractor |
Wing Tat Civil Engineering Co. Limited |
Environmental Team (ET) |
Aurecon Hong Kong Limited |
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
§ Site Clearance Work
§ Lifting Operation;
§ Plant Operation;
§ Excavation; and
§ Sheet Piling.
Lin Fa Tei
§ Site Clearance Work
§ Lifting Operation;
§ Plant Operation; and
§ Excavation.
Tai Wo
§ No construction activities.
Sung Shan New Village
§ No construction activities.
Table 2.1 Summary of Impact Water Quality Monitoring Stations
Stream |
Monitoring ID |
Coordinates (HK Grid) |
Remarks |
|
Easting |
Northing |
|||
SSNV |
C1A (1) |
821702 |
831945 |
Alternative Impact Monitoring Point |
C2 |
822459 |
831470 |
Control Monitoring Point |
|
C3A (2) |
822413 |
831284 |
Alternative Control Monitoring Point |
|
TW |
C4 (4) |
825497 |
830664 |
Control Monitoring Point |
C5 (4) |
825486 |
830716 |
Impact Monitoring Point |
|
LFT |
C6 |
827232 |
831713 |
Control Monitoring Point |
C7A (3) |
826865 |
832115 |
Alternative Control Monitoring Point |
|
C8 |
826513 |
832075 |
Impact Monitoring Point |
|
HC |
C9 |
828304 |
835029 |
Control Monitoring Point |
C10 |
827919 |
834271 |
Impact Monitoring Point |
Notes:
(1) At Station C1, access to safe sampling of water is not feasible due to steep banks on both sides of the stream channel. An alternative monitoring location is proposed at Station C1A, which is about 250 m along the same stream channel downstream of Station C1 and is accessible for safe water sampling.
(2) During the first day of baseline monitoring at Station C3, shallow water was observed, and the ET could not sample enough water for monitoring. As agreed by the ER, the Contractor, and the IEC, a new sampling location, Station C3A, was identified at about 130 m upstream and was accessible for water sampling.
(3) For Station C7, the location is not close to the nearest, revised works boundary (about 200 m away). An alternative monitoring location is proposed at Station C7A, which is about 23 m upstream of the nearest, revised works boundary.
(4) Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No.: EP-596/2021. Hence, monitoring for Station C4 & Station C5 are only required during dry season (i.e. October to March).
Table 2.2 Parameters measured in the Impact Water Quality Monitoring
Parameter |
Frequency |
Duration |
Dissolved oxygen (DO), temperature, turbidity, salinity, pH, stream water depth and suspended solids (SS) |
3 days in a week |
Throughout the construction phase |
Table 2.3 Action and Limit Levels for Water Quality
Parameters |
Action Level |
Limit Level |
DO in mg/L |
< 5%-ile of baseline data |
< 4 mg/L or < 1%-ile of baseline data |
SS in mg/L |
> 95%-ile of baseline data or >120% of upstream control station of the same day |
> 99%-ile of baseline data or 130% of upstream control station of the same day |
Turbidity in NTU |
> 95%-ile of baseline data or >120% of upstream control station of the same day |
> 99%-ile of baseline data or > 130% of upstream control station of the same day |
Notes:
(1) For DO, non-compliance of the water quality limit occurs when monitoring result is lower than the limit.
(2) For SS and turbidity, non-compliance of the water quality limit occurs when monitoring result is higher than the limit.
(3) All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered necessary.
Table 2.4 Action and Limit Levels of Water Quality
Monitoring ID |
Parameters |
Action |
Limit |
|
SSNV |
C1A |
DO in mg/L |
6.72 |
4 (1) |
SS in mg/L |
7.3 or >120% of upstream control station of the same day |
8.5 or > 130% of upstream control station of the same day |
||
Turbidity in NTU |
10.37 or >120% of upstream control station of the same day |
10.81 or > 130% of upstream control station of the same day |
||
TW |
C5 |
DO in mg/L |
8.36 |
4 (2) |
SS in mg/L |
9.9 or > 120% of upstream control station of the same day |
10.0 or > 130% of upstream control station of the same day |
||
Turbidity in NTU |
13.64 or > 120% of upstream control station of the same day |
13.87 or > 130% of upstream control station of the same day |
||
LFT |
C8 |
DO in mg/L |
5.38 |
4 (3) |
SS in mg/L |
6.3 or > 120% of upstream control station of the same day |
7.0 or > 130% of upstream control station of the same day |
||
Turbidity in NTU |
12.46 or > 120% of upstream control station of the same day |
12.94 or > 130% of upstream control station of the same day |
||
HC |
C10 |
DO in mg/L |
2.55 |
2.43 (4) |
SS in mg/L |
8.7 or > 120% of upstream control station of the same day |
8.8 or > 130% of upstream control station of the same day |
||
Turbidity in NTU |
20.06 or > 120% of upstream control station of the same day |
21.07 or > 130% of upstream control station of the same day |
(1) The 1%-ile of baseline DO data at C1A is 6.61 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(2) The 1%-ile of baseline DO data at C5 is 8.09 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(3) The 1%-ile of baseline DO data at C8 is 5.36 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(4) The 1%-ile of baseline DO data at C10 is 2.43 mg/L, which is lower than 4 mg/L. Taking account of the baseline water quality condition and to minimise any false alarm of water quality deterioration during construction phase, DO concentration of 2.43 mg/L is adopted as the limit level.
Table 2.5 Summary of Exceedance Records of Water Quality Monitoring
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedance related to the Project |
Total No. of exceedance related to the Project |
||
AL |
LL |
AL |
LL |
|||
Dissolved Oxygen |
2 |
1 |
3 |
0 |
0 |
0 |
Turbidity |
0 |
1 |
1 |
0 |
0 |
0 |
Suspended Solids |
2 |
11 |
13 |
0 |
0 |
0 |
Table 2.6 Comparison of the difference between the quarterly mean and 1.3 times of the ambient mean
Parameter |
Monitoring Location |
Quarterly Mean of SS (mg/L) |
Baseline Level of SS (mg/L) |
1.3 Times of Ambient Mean (mg/L) (1) |
Quarterly Mean of SS > 1.3 Times of Ambient Mean (Y/N) |
Request of Further Mitigation Measures (Y/N) |
Suspended Solids |
C1A |
14.0 |
4.8 |
6.2 |
Y |
N |
C2 (Control Point) |
13.8 |
3.2 |
4.2 |
Y |
N/A |
|
C3A (Control Point) |
9.9 |
2.2 |
2.9 |
Y |
N/A |
|
C4 (Control Point) |
10.7 |
10.7 |
13.9 |
N |
N/A |
|
C5 |
13.4 |
5.2 |
6.8 |
Y |
Y |
|
C6 (Control Point) |
11.7 |
3.7 |
4.8 |
Y |
N/A |
|
C7A (Control Point) |
14.6 |
6.7 |
8.7 |
Y |
N/A |
|
C8 |
12.0 |
4.0 |
5.2 |
Y |
N |
|
C9 (Control Point) |
14.4 |
5.9 |
7.7 |
Y |
N/A |
|
C10 |
10.1 |
8.5 |
11.1 |
N |
N |
Notes:
(1) 1.3 times of the ambient mean equal to be defined as 30% increase of the baseline data.
Sung Shan New Village (Station C1A, C2 & C3A)
Tai Wo (Station C4 & C5)
Lin Fa Tei (Station C6, C7A & C8)
Ha Che (Station C9 & C10)
Table 3.1 Noise Monitoring Stations during Construction Phase
ID No. (1) |
Location |
Nature of Uses |
Type of Measurement |
SSNV_M2 |
Village house next to a nullah in Tong Tai Po Tsuen (near DD118 1720 S.A) |
Residential |
Façade |
SSNV_M3 |
Village house near a soybean sauce factory in Sung Shan New Village (near DD118 1712) |
Residential |
Façade |
SSNV_M6 |
#43, Sung Shan New Village |
Residential |
Free-field |
TW_M2 |
#200, Cheung Po |
Residential |
Free-field |
TW_M3 |
Kai Yip Garden, #3H, Tai Wo |
Residential |
Free-field |
LFT_M1 |
#2G, Lin Fa Tei |
Residential |
Façade |
LFT_M3A (2) |
Near #125B, Lin Fa Tei |
Residential |
Free-field |
LFT_M5 |
#156B, Lin Fa Tei |
Residential |
Façade |
LFT_M7 (3) |
Village house near the nullah (DD112 699 S.E) |
Residential |
Façade |
LFT_M11 (2) |
#210, Ngau Keng Tsuen |
Residential |
Façade |
HC_M3A (2) |
Next to DD111 326 S.B RP near Fan Kam Road |
- |
Free-field |
HC_M4 |
#1C, Chuk Hang |
Residential |
Façade |
HC_M6 |
The Arbutus House 12, #52, Shui Kan Shek |
Residential |
Façade |
Notes:
(1) SSNV – Sung Shan New Village; TW – Tai Wo; LFT – Lin Fa Tei; HC – Ha Che.
(2) LFT_M3A, LFT_M11, HC_M3A and are alternative noise monitoring stations proposed to replace LFT_M3, LFT_M13 and HC_M3, respectively.
(3) The noise monitoring at LFT_M7 have been suspended since 27 March 2024 due to the objection from property management office for providing access to designated monitoring location. The noise monitoring at LFT_M7 will be resumed when the access to the monitoring location is granted.
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
Monitoring Station |
Parameter |
Frequency and Duration |
HC_M3A, HC_M4, HC_M6, TW_M2, TW_M3, LFT_M1, LFT_M3A, LFT_M5, LFT_M7 and LFT_M11 |
Leq(30mins) (as a logarithmic average of 6 consecutive Leq(5mins)) |
Once every week throughout the construction phase between 0700 and 1900 on normal weekdays |
Table 3.3 Action and Limit Levels for Construction Noise Monitoring
Time Period |
Action |
Limit Level |
07:00 – 19:00 on normal weekdays |
When one or more documented complaints are received |
75 dB(A)(1) |
07:00 – 23:00 on holidays; and 19:00 – 23:00 on all other days |
45 dB(A)(2) |
|
23:00 – 07:00 of the next day |
30 dB(A)(2) |
Notes:
(1) Between 07:00 and 19:00, construction noise limit for school during normal term time is 70 dB(A) and 65 dB(A) during examination period.
(2) The ASR of identified noise sensitive receivers is “A”, which is a rural area that is not affected by the in Influencing Factors (Ifs). The limit levels are stipulated in the Technical Memorandum on Noise from Construction Work in Designated Areas.
Post-translocation Monitoring
Table 8.1 Mitigation Measures for Impacted Graded Historic Buildings
Graded Historic Buildings |
Mitigation Measures |
Lee Tat Bridge, Shui Tsan Tin (Grade 3) |
§ A condition survey should be carried out in advance of works and after completion of works by qualified building surveyor or structural engineer. The Condition Survey Report should contain descriptions of the structure, identification of fragile elements, an appraisal of the condition and working methods for any proposed monitoring and precautionary measures that are or were recommended with aid of photo records. The condition survey report must be submitted to the AMO for comment before construction activities commence and after the works have been completed. The contractor should implement the approved monitoring and precautionary measures. § Vibration, settlement and tilting monitoring should be undertaken during the construction works to ensure that safe levels of vibration are not exceeded. An Alert, Alarm and Action (AAA) vibration limit set at 5 / 6 / 7.5 mm/s for Grade 3 historic buildings, settlement limit set at 6/ 8/ 10mm, and tilting limit set at 1/2000; 1/1500; 1/1000 should be adopted. Monitoring proposal, including checkpoint locations, installation details, response actions for each of the AAA levels and frequency of monitoring should be submitted for AMO's consideration. Installation of monitoring checkpoints shall be carried out in great care and adequate protection shall be provided so as to avoid unnecessary disturbance/ damage to the historic fabrics. Photo records of monitoring checkpoints shall be submitted upon installation for AMO's records. Monitoring records should be submitted to AMO on regular basis and alert AMO should the monitoring reach AAA levels. |
Lan Fong Study Hall, Chuk Hang (Grade 3) |
|
St John’s Chapel, Cheung Po (Grade 2) |
Table 9.1 Site Observations
Date |
Environmental Observations |
Follow-up Status |
21 February 2024 |
Observation(s) and Recommendation(s)
Nil |
Nil |
28 February 2024 |
Observation(s) and Recommendation(s)
Nil |
Nil |
6 March 2024 |
Observation(s) and Recommendation(s)
Nil |
Nil |
15 March 2024 |
Observation(s) and Recommendation(s)
Ha Che: 1. Oil stain should be removed and treated as “Chemical Waste”. |
Ha Che: Oil stain had been removed and treated as “Chemical Waste”. |
20 March 2024 |
Observation(s) and Recommendation(s)
Lin Fa Tei: 1. General rubbish bin should be enclosed and labeled properly. |
Lin Fa Tei: 1. General rubbish bin had been enclosed and labeled properly. |
22 March 2024 |
Observation(s) and Recommendation(s)
Nil |
Nil |
26 March 2024 |
Observation(s) and Recommendation(s)
Ha Che: 1. Dusty material should be covered by tarpaulin. |
Ha Che: 1. Dusty material had been covered by tarpaulin. |
3 April 2024 |
Observation(s) and Recommendation(s)
Nil |
Nil |
10 April 2024 |
Observation(s) and Recommendation(s)
Lin Fa Tei: 1. Inert materials nearby the drainage should be removed regularly to prevent surface run-off. 2. The stagnant water within the material storage zone should be removed or pumped. |
Lin Fa Tei: 1. Inert materials nearby the drainage should be removed regularly to prevent surface run-off. 2. The stagnant water within the material storage zone had been removed. |
17 April 2024 |
Observation(s) and Recommendation(s)
Nil |
Nil |
24 April 2024 |
Observation(s) and Recommendation(s)
Lin Fa Tei: 1. The NRMM label should be displayed on excavator “BH03” clearly. |
Lin Fa Tei: 1. The NRMM label had been displayed on excavator “BH03” clearly. |
Table 10.1 Summary of Exceedance Records of Water Quality Monitoring
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedance related to the Project |
Total No. of exceedance related to the Project |
||
AL |
LL |
AL |
LL |
|||
Dissolved Oxygen |
2 |
1 |
3 |
0 |
0 |
0 |
Turbidity |
0 |
1 |
1 |
0 |
0 |
0 |
Suspended Solids |
2 |
11 |
13 |
0 |
0 |
0 |
Noise
§ Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and
§ Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
§ No effluent discharge would be allowed before acquired the effluent discharge license;
§ Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;
§ Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;
§ Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;
§ Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and
§ Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.
Waste Management
§ Provision of sufficient waste disposal points and regular collection of waste;
§ Regular cleaning and maintenance programme for drainage system; and
§ Chemical containers shall be stored with drip tray underneath.
Ecology
§ Minimize loss of habitats and associated wildlife; and
§ Using directional lighting to prevent excessive light spill into adjacent natural habitat and disturbance to nocturnal fauna.
Landscape and Visual
§ Construction activities shall be carefully designed to minimize impact on existing retained trees; and
§ Adequate tree protection measures shall be provided for the trees to be retained on site.